For the 1D channels the Courant criterion is expressed in the form:
1 D Scheme (2)
The time step selected should not be greater than the minimum value for any channel (except non-inertial channels such as bridges, culverts, etc). Accuracy of the results is also influenced by time step. The limiting value adopted is usually a compromise between accuracy, stability and simulation time, and sensitivity checks are recommended. The occurrence of mass errors may indicate the use of too high a timestep (see Section 6.4.4).

Typical timestep values are 60 or 120 seconds for a model with a minimum channel length of 500 metres, down to 1 second for 1D domains with small pipes. Where a few channels must be much shorter than the rest, it may be economical to specify them as non-inertial channels. The timestep can then be chosen on the requirements of the shortest remaining channel. Care should be exercised when specifying non-inertial channels to ensure that errors are not introduced by the non-inertial representation, particularly if these channels are in a region of particular interest. Any approximations can usually be assessed by a few selected runs without the non-inertial approximation and with the necessary shorter time step.



Yüklə 4,62 Mb.

Dostları ilə paylaş:
1   ...   33   34   35   36   37   38   39   40   ...   303




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©azkurs.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin