Dynamic motion. During the lift off the vessel/barge deck, through the splash zone and lowering
through the upper sections of the water column, the lifted equipment should be controlled using tugger
or control lines. Set down loads shall be calculated based on the heave response of the lifted
equipment in the water column, and the set down speeds established to limit impact loads on the
equipment, host structures and/or guidance systems.
19.3.7
Natural frequency. For deep-water installations the natural frequency changes as the lifted
equipment is lowered through the water column. Installation analyses should be undertaken to
determine if there is a possibility of resonance. When resonance is possible the effects shall be
quantified and mitigating measures identified to overcome its effects.
19.3.8
Phasing. For deep-water lowering operations the effects of phasing between the boom tip and the
lifted object shall be investigated by analysis and limiting seastates identified. Special lifting slings,
ropes and devices may be needed to limit these effects.
19.3.9
Mid-water load transfer is possible for any item, but this shall be carried out at a depth so that any
lateral load on a rigging or crane system is minimised.
19.3.10
Dropped objects. Consideration shall be given to the safety of existing equipment and pipelines on
the seabed during overboard lifting operations. Where appropriate, the structure should be lifted
overboard and lowered a safe horizontal distance from any existing subsea equipment and pipelines
and then moved into the final position at a suitable height above the sea bed.
19.4 DEPLOYMENT SYSTEM 19.4.1
The deployment system shall be capable of raising the structure off the vessel deck and over-boarding
through the splash zone and to its final location with sufficient motion control.
19.4.2
The deployment system shall also be capable of a complete reversal in the event of any unforeseen
event taking place.
19.4.3
A dual deployment system, where the structure is lifted off the deck, lowered through the splash zone
to a suitable depth below the sea surface using the crane and then transferred to a deployment winch
for the remaining lowering to the seabed, is acceptable.
19.4.4
The crane shall be certified for its intended function and load-radius curves shall be provided. In
certain cases this may include different vessel roll angles or DAF values.
19.4.5
If a deployment winch is chosen for lowering a structure to the seabed it must satisfy the same
requirements as a crane, in terms of redundancy, FMEA, capacity and DAF.
19.4.6
Load cells on deployment winches shall be calibrated annually against certified load cells and load test
certificates made available to the attending surveyor.