3.Site management

3.1Traffic Control


General: Traffic control shall be undertaken in accordance with the approved Traffic Management Plans and Permits.

Method: Provide for traffic while undertaking the works in accordance with the requirements of Manual of Uniform Traffic Control Devices (Queensland), Part 3: Works on Roads.


3.2Temporary Surfacing


All roads, footways, bikeways and other accessible areas must be made safe for the passage of vehicle and pedestrian traffic before the area is opened to traffic, either temporarily or permanently.

All surfaces opened to vehicles or pedestrians must be either permanently or temporarily sealed. Reinstatement of the final permanent surface may be delayed while the full length of the service is being installed and until testing is completed. Any temporary restorations must have a level and sealed surface that is flush with the surrounding surface. Use steel plates, turf, cold mix asphalt or hot mix asphalt. It is not acceptable to leave gravel, crusher dust, “deco”, any other unbound material or lean mix concrete exposed as the temporary surfacing.

Use of steel plates must comply with Brisbane City Council Technical Note, TN01 Temporary Access Covers.


Yüklə 73,69 Kb.

Dostları ilə paylaş:
1   2   3   4   5   6   7   8   9   10   ...   32




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©azkurs.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin