Evaluation Control Measures / Operating Procedures Action By Residual Risk Evaluation Additional Recommend ations Action Implemented (Y/N) & Signature [ continuation] C - 5 1. Commissioning PTW.
COMM
OPER
B - 4 -
2. Live Lines Identified.
COMM
3. LOTO isolation procedure and register under LOTO Coordinator
responsibility.
COMM
4. Emergency Response Plan.
HSE
5. Wind socks.
HSE
6. Commissioning awareness.
HSE
7. Regular check for battery limit valves hydrocarbon isolation integrity and
recording. Twice per shift.
HSE
8. Risk notification (Safety Alert, STARRT, Tool Box Talk).
HSE
CONSTR
9. Barricade and Access Control / Signages.
HSE
10. Removal of all temporary facilities, mainly electrical devices /
housekeeping
CONSTR
11. Firewater U/G and related FF equipment in service.
COMM
12. Fire&Gas Detection System in service.
COMM
13. Scaffolding removed or if necessary wood boards to be replaced with
metal type.
CONSTR
14. Antispark tools
CONSTR
15. Pre-Commissioning/Commissioning detailed procedure / Work Method
Statement to be followed
COMM
16. Equipment / Tools colour coding to be ensured.
COMM
Figure 3: SIMOPS Risk Assessment Worksheet In addition, dedicated SIMOPS layout was discussed and refined during the workshop. As per below Figure 4,
it consists of plant layout showing concerned information and countermeasures identified for safe SIMOPS
execution as: areas affected by hydrocarbon-in, prevailing wind direction, distribution of expected manning
level, barricade areas, access control plan, traffic control philosophy including access available for rescue
team, muster points, etc.
Both above documents were tailored for the subject project with the aim to provide site personnel and site
management with quick and easy readable reference tool.
119