V2 = P Hk2 ctg αsr
P – yotqiziqning perimetri P = 2 (L + m)
V3 – karerning burchakdagi uchastkalarida joylashgan aloxida qismlarga bo‘lingan konusning yig‘ma hajmi (V3 va V3″ ) m3
V3 = Hk3 ctg2αsr
αsr – ish olib borilmaydigan bortning qiyalik burchagi
Karer yig‘indi hajmi
Vk = S Hk + P Hk2 ctg αsr + Hk3 ctg2αsr
S = Lm = 1500 • 45 = 67500 m2
P = 2 (L + m) = 2 • (1500 +45)= 3090 m
Vk = S Hk + P Hk2 ctg αsr + Hk3 ctg2αsr =67500 • 750 + • 3090 •750 2 • ctg 55o + • 7503 • ctg2 55o =865687500 m3
Karer maydoni uzunligi
Lk = L + 2Hk • ctg αsr = 1500 + 2 • 750 • ctg 55o = 2550 m
YUqori qismi bo‘yicha karer kengligi
Bk = m + 2Hk • ctg αsr = 45+ 2 • 750 • ctg 55o = 1095 m
Karer konturidagi foydali qazilma hajmi
Vpi = S (Hk – hn)= 67500 • (750- 20) = 49275000 m3
Karer konturidagi foydali qazilma sanoat zaxirasi
Qpi = Vpi ρi ηi = 49275000 • 2.8 • 0.93= 128312100 t
Karer konturidagi tog‘ jinsi hajmi
Vp = Vk – Vpi =865687500 –49275000= 816412500 m3
O‘rtacha qoplovchi tog‘ jinsi koeffitsienti
ksr = Vp / Qpi =816412500 / 128312100= 6 m3/t
Qoplovchi tog‘ jinsi bo‘yicha karerning ishlab chiqarish unumdorligi
Pv = Ppi ksr kn = 5 • 106 • 6• 1.2= 36• 106 = 360 • 105 m3/yil
kn = 1.1 ÷ 1.3
Kon massasi bo‘yicha karerni ishlab chiqarish unumdorligi
Pgm= Ppi + Pv = 5 • 106 • +360 • 105 = 37785714 m3/yil
Karerning foydali qazilma bo‘yicha sutkalik unumdorligi
Ppis = Ppi / Tg = 5• 106 / 350 = 14286 t/sutka
Tg = 350 kun
Qoplovchi tog‘ jinsi bo‘yicha karerning sutkalik ish unumdorligi
Pvs = Pv / Tg = 360 • 105 / 350 = 102857 m3/sutka
Foydali qazilma va qoplovchi tog‘ jinsi bo‘yicha karerning smenalik ishlab chiqarish unumdorligi
Ppism = Ppis / nsm = 14286 / 2 = 7143 t/smena
Pvsm = Pvs / nsm = 102857 / 2 = 51428m3/smena
nsm = 2
Karerni xizmat qilish muddati
Tsl = Ts + Te + Tz
Te = Qpi / Ppi = 128312100 / 5 • 106 26 yil
Kapital transheya hajmini hisoblash
Kapital transheya hajmi
V1 = bt ht2 / 2i
bt – transheya asosi kengligi
ht – transheya chuqurligi
i – kapital transheya qiyaligi
V1 = 35 • 132 / 2 • 0.038 = 103618 m3
Piramida hajmi
V2 = ht3 / 6itgαt = 133 / 6 • 0.038 • 0.46 = 2145 m3
Berilgan Vt = V1 + 2V2 formuladan transheya hajmi aniqlanadi
Vt = 77828+ 2 • 2145 = 107908 m3
Qirqim transheya o‘tish ko‘rsatkichlarini va parametrlarini hisoblash
12 soat
2 smena
dc = 200 mm
Hu = 15 m
Skvajina uzunligi
Lc = Hu + lper = 15 + 2.2 17,0 m
Perebur uzunligi
lper = 11dc = 11 • 0.2 = 2.2 m
Kolonkali zaryad uzunligi
lzar = Lc – lzab = 17,2 – 4,6 = 12,6m
Zaboyka uzunligi
lzab = 0,27Lc = 0,27 • 17,2 = 4,6 m
Qatordagi zaryad massasi
Qzo = ρlzar = 21,37 • 12.6 = 269 kg
Qzv = ρlzar = 21,37 • 17.2 = 367 kg
Zaryad massasining o‘rtacha qiymati
Qzs = = 288.6 kg
Bitta zaryad yordamida ajratib olinadigan tog‘ jinsi hajmi
V1zar = Qzs / qp = 288.6/ 0.9 = 320.6m3
Bitta skvajina qatori yordamida ajratib olinadigan tog‘ jinsi hajmi
V5zar = 320.6 • 5 = 1603 m3
Zaboyda yuklash sharoitida ekskavatorni ish unumdorligi
Texnik ish unumdorligi
Pet = E kcn = • 15• • 0.7 = 675 m3/soat
Ekskavatorni smenali ekspluatatsion ish unumdorligi
Pesm = Pet Tsm ki = 675• 12 • 0.75 = 6075m3/smena
Ekskavatorni sutkalik ish unumdorligi
Pesut = Pesm nsm = 6075 • 2 = 12150 m3/sut
Ekskavatorni oylik ish unumdorligi
Pemes = Pesut •27 = 12150 • 27= 328050 m3/oy
Transheyani o‘tish tezligi
V = = 328050/ 682.5 = 480.6 m/oy
St = Hy (Bt + Hy ctgα)= 15 • (35 + 15 • ctg 55o)= 682.5 m2
Bt = 35 m Ht = Hy
Ish olib boriladigan va ish olib borilmaydigan bortlar konstruksiyasi
Ish olib boriladigan bortning balandligi
Nrb = Nu nru = 15 • 50 = 750 m
Kon massasini avtomobil transportiga yuklashda ishchi maydon kengligi
SHrp = Vr + S + T + S + Z + SHvb = 23 + 2.5 + 12 + 1.5 + 6.6 + 4 = 49.6 m
Vr – tj uyumi kengligi
S – transport yo‘lagi va uyumlarning quyi brovkasi orasidagi xavfsizlik kengligi (2 – 3 m)
T – transport yo‘lagi
S – xavfsizlik oralig‘i (1.5 – 2 m)
Z – prizmaning emirilish kengligi
Z = Hy (ctgy α – ctg α) = 15 • (ctgy 55o – ctg 75o) = 6.6 m
Ish olib boriladigan bort qiyaligining gorizontal qo‘yilgan o‘lchami
Srb = Hy ctg α nru + SHrp (nru - 1) = 15 • 0.46 • 50 + 49.6 • (50 - 1)= 2775.4m
Karerning ish olib boriladigan bortining tangens burchagi
tg φ = Hrb / Crb = 750 / 2775.4 = 0.27023 = tg 15o
Ish olib borilmaydigan bort balandligi
Nnb = Nu nnu = 15 •50 = 750 m
Ish olib borilmaydigan bort qiyaligining gorizontal qo‘yilgan o‘lchami
Snb =nnu(Nuctgαy+vs)+(nnu – 1)vb=50 • (15 • ctg 55o+5)+(50 - 1) • 5= 1027 m
vs – s’ezd kengligi
vb ≥ Hy = • 15 = 5 m
Ish olib borilmaydigan bort qiyalik burchagining tangensi
tg α = Hnb / Snb = 750/ 1027 = 0,73 = tg 37o
Burg‘ulash stanogining ish unumdorligini hisoblash
Burg‘ulash ko‘rsatkichlari
Pb = 0,07 (σsj + σsd) + 0,7γ
Tog‘ jinsi qattiqligi f = 14 bo‘lganligi uchun SBU-160 havo bilan tozalovchi zarbli aylanma burg‘ulash stanogini tanlaymiz. Bunda (f=10÷20)
f = σsj / 10 bundan
σsj = f 10 = 14 • 10 = 140 MPa
σrast = 0,1 σsj = 0,1 • 140 = 14 MPa
σsd = 0,2 σsj = 0,2 • 140 = 28 MPa
Pb = 0,07 (σsj + σsd) + 0,7γ = 0,07 • (140 + 28) + 0,7 • 3 = 13.86
Pb = 10.1 ÷ 15 gacha bo‘lsa, III – sinf qiyin burg‘ulanuvchi tog‘ jinsi
O‘qqa beriladigan optimal kuch
Po ≥ k Pb dd = 0,75 • 13.8 • 2002 = 414 kN
dd – dolota diametri
Pb – burg‘ulash ko‘rsatkichi
k - burg‘ulash ko‘rsatkichiga bog‘liq bo‘lgan koeffitsient
Pb = 13.8 bo‘lganda k = 0,75 ga teng
Burg‘ulashning texnik tezligi
vb = 3.5 Po nv / Pb dd2 = 3,5 • 230 • 60 / 12 • 162 = 15,7 m/s
Po – o‘qqa berilgan optimal kuchlanish kN
nv – burg‘ulash stavining optimal aylanish chastotasi min-1
Pb – tog‘ jinsining burg‘ulanish ko‘rsatkichi
dd – dolota diametri sm
Berilgan Tsm , Tpz , Tr , Tv kattaliklar va olingan vb ko‘rsatkichi bilan stanokning smenalik unumdorligi topiladi
Absm = = =121,5 m/smena
Burg‘ulash stanogining sutkalik unumdorligi
Abs = Absm nsm = 121,5 • 2 = 243 m/sutka
nsm – smenalar soni
Burg‘ulash stanogining yillik ish unumdorligi
Aby = Abs nrds = 243 • 250 = 60750 m/yil
nrds – stanokning yillik ish kunlari soni 250 kun
Talab qilinayotgan ish hajmini bajarish uchun kerak bo‘ladigan stanoklar soni
NBS = = = 24 ta
VGM – burg‘ulangan kon massasining yillik hajmi VGM = PGM
qGM – 1 p.m. skvajinadan chiqadigan portlatilgan kon massasi
Burg‘ulash stanogining ishchi parki
Nbr = Nbs / krez = 24/ 1,4 = 17 ta
krez – burg‘ulash stanogining rezerv koeffitsienti
krez = Ty / nrds = 350 / 250 = 1,4
Ty - karerda bir yildagi ish kunlari soni 350 kun
Skvajina zaryadlarini hisoblash
SBU-160 stanogi dolotasi diametri bo‘yicha portlovchi skvajina diametri aniqlanadi
dc = dd krazb = 200 • 1,03 = 206 mm
krazb – tog‘ jinsi qattiqligiga bog‘liq holda qabul qilinuvchi burg‘ulash koeffitsienti f = 14 da krazb = 1,03 ga teng
Perebur uzunligi
lper = 11 dc = 11 • 206 = 2266 mm ≈ 2 m
Skvajina chuqurligi
lc = Hu + lper = 15 + 2 = 17 m
Zaboyka uzunligi
lzab = 0,27 lc = 0,27 • 17 = 4,59 m
Skvajinadagi PM zaryadi uzunligi
lzar = lc – lzab = 17 – 4,59 = 12,41 m
Etalondagi portlovchi moddaning solishtirma sarfi (q‵, kg/m3) aniqlanib, qabul qilingan portlovchi moddaning solishtirma sarfi (qp, kg/m3) aniqlanadi
qp = q’kvv = 0,9 • 1,08 = 0,97 kg/m3
kvv – PM turini hisobga oluvchi koeffitsient
f = 14 bo‘lganda pog‘ona balandligi Nu = 15 m bo‘lganligi uchun PM turi Ifzanit T-80 α = 70o kvv = 1,08
Pog‘ona asosi bo‘yicha qarshilik chizig‘i kattaligi
W = 0.9 = 0,9 • = 5 m
Asos bo‘yicha qarshilik chizig‘i kattaligi quyidagi shartlar bo‘yicha tekshiriladi: W ≥ Wmin
Wmin = Hy ctg α + 2 = 15 • ctg 55o + 2 = 12.5 m
W ˂ Wmin bo‘lsa u holda W = Wmin deb olamiz
Skvajinaning solishtirma sig‘imi
ρ = 7.85dc2∆ = 7.85 • 2.062 • 1 = 33.31 kg/m
∆ - skvajinadagi zaryad zichligi kg/dm3
lper kattaligini tekshirish quyidagi shart bo‘yicha bajariladi
lper ≤ 0,3W
0,3 • 5 = 1,5 m
lper = 1,5 m deb qabul qilamiz va qaytadan hisoblaymiz
lc = Hu + lper = 15 + 1,5 = 16,5 m
lzab = 0,27 lc = 0,27 • 16,2 = 4,45 m
lzar = lc – lzab = 16,2 – 4,45 = 12.05 m
Skvajinadagi zaryad massasi
Qz = ρlzar = 33.31 • 12.05 = 401 kg
Qatordagi skvajinalar orasidagi masofa
a = = = 5.5 m
Skvajinalarning ruxsat etilgan yaqinlashish koeffitsienti bo‘yicha a kattalik tekshiriladi
m = 1÷ 1.1
m = a / W = 5.5 / 5 = 1,1
Uyum kengligi
Bp ≈ kz kv Nu = 0,3 • 3 • • 15 = 13,2 m
kz = 0,3
kv =2,5 - 3
Uyum balandligi
hp ≈ = 2 •15 • 5• 1,5 / 13,2 =17 m
kp = 1,4 – 1,6
1 p.m skvajinani portlatganda chiqadigan kon massasi
qgm = = = 25 m3/m
Ekskavator turini tanlash, karer ekskavatorlarini unumdorligini hisoblash
Ekskavatorning texnik ish unumdorligi
AT = ke = • 0,7 = 1350 m3/s
Ekskavatorning smenalik ish unumdorligi
Asm = AT Tsm ki = 1350 • 12 • 0,75 = 12150 m3/smena
ki = 0,75
Ekskavatorning sutkalik ish unumdorligi
As = Asm nsm = 12150 • 2 = 24300 m3/sutka
Ekskavatorning yillik unumdorligi
Ay = As ny = 24300• 250 = 6075000m3/yil
Ekskavator parki
Nes = Pgm / Ay = / 6075000= 6 ta
Ekskavatorning ishchi parki
Ner = Nes / krez = 6/ 1,4 = 4 ta
Ekskavatorning o‘tish kengligi
Az = (0,8 ÷ 1,2) Rchu = 1,2 • 19.5 = 23.4 m
Hy ≤ 1,5 Nchmax 15 ≤ 1,5 • 15.8 15 ≤ 23.7