MUNIS

Equipment  

The applicants should provide cost justification for each piece of equipment and describe how it will 

be used (e.g., list specific project tasks).  The cost of equipment can include installation, assembly, 

tuning,  launching,  certification,  and  maintenance  costs.  The  installation  and  operation  of  the 

equipment should conform to the standards and requirements of RUZ and the World Bank.   

The requirements for equipment: 

a)  Must be new and conform to the objectives of the subproject; 

b)  Must contain all the necessary units and components; 

c)  The cost should include the cost of delivery, installation, and maintenance of the equipment for 

the entire period of the project; 

d)  It should be possible to dismantle and re-install the equipment without significant cost losses; 

e)  The equipment must ensure the quality of production that complies with RUZ or international 

standards; 

f)  The equipment must have a certificate of origin from the manufacturer or an authorized dealer 

in the territory of RUZ; 

g) The equipment purchase must be accompanied by a warranty and post-warranty service, staff 

training, the availability of prompt repairs, troubleshooting, etc.; and  

h) The installation and operation of the equipment must comply with the environmental standards 

and the requirements of RUZ and the Bank. 

 

The equipment purchased at the expense of Grant funds should be used exclusively for 



project/subproject purposes during the implementation period.   

 

 



 


 

12 


 




Yüklə 0,73 Mb.

Dostları ilə paylaş:
1   ...   6   7   8   9   10   11   12   13   ...   38




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©azkurs.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin