GUIDELINES
FOR
MARINE
LIFTING
&
LOWERING
OPERATIONS
0027/ND Rev 11
Page 19 of 84
DP audit documentation and FMEA analysis and DP procedures detailing positioning systems
(see Section 13.8 of 0001/ND, Ref. [1].)
The limiting design weather conditions proposed and the anticipated
behaviour of the crane
vessel and the transport barge or vessel carrying the structure in those conditions.
The arrangements for handling and mooring the transport barge or vessel alongside the crane
vessel.
The arrangements for cutting seafastenings before lifting.
The management structure for the operations and Management of Change procedures.
ROV performance documentation.
Risk assessments, HAZOP / HAZID studies involving key personnel of all relevant parties.
Simultaneous Marine Operations (SIMOPS).
The completion of the preparations at the installation location to receive the structure.
4.2.2
The information required in order to issue a Certificate of Approval is listed in Appendix A.
4.2.3
Technical studies leading to the issue of a Certificate of Approval may consist of:
a.
Reviews
of specifications, procedures and calculations submitted
by the client or his
contractors, or
b.
Independent analyses carried out by GL Noble Denton to verify the feasibility of the proposals,
or
c.
A combination of third party reviews and independent analyses.